Link activities =============== .. index:: Link activities Activities can be linked with each other in Gantt chart, network charts and Gantt-network charts. The following link types are at your disposal: +-----------------------------------+--------------------------------------------------------------------------------------------+ | **Finish-Start** | the "from" activity must finish before the "to" activity can start | +-----------------------------------+--------------------------------------------------------------------------------------------+ | **Start-Start** | the "from" activity must start before the "to" activity can start | +-----------------------------------+--------------------------------------------------------------------------------------------+ | **Finish-Finish** | the "from" activity must finish before the "to" activity can finish | +-----------------------------------+--------------------------------------------------------------------------------------------+ | **Start-Finish** | the "from" activity must start before the "to" activity can finish | +-----------------------------------+--------------------------------------------------------------------------------------------+ | **Incompatible activity group** | Activities that must not be executed at the same time (time conflicts) | +-----------------------------------+--------------------------------------------------------------------------------------------+ You can unhide the Properties window of any link by doubleclicking on the link. |image0| **Time intervals** Intervals can be defined in Project properties in relation to the time unit of the duration (such as hours or days). You can choose among the following types of intervals: - in absolute time (1 day consists of 24 hours, that is, for example, 8 hours and 16 non-working hours) - in calendar time (depending on the actual calendar, for example, 1 day consists of 8 hours, that is, it ignores non-working hours) - in relative time (for instance, a particular percentage, relating to the "to" activity, such as: 50%) **Intervals can have** - positive (such as: + 2 hours) or - negative (such as: - 50% = overlapping) signs. **Highlight link** Links can be highlighted by means of colour or boldface. **Create link** In order to create a new link, do as follows: - Choose the link type via the menu **Start > Insert > Link**. |image1| - Connect two activities by drawing your mouse from one activity to another. - Choose the interval type for the link in the Properties window. - If necessary, enter the Delay (positive or negative) by which you want to delay the "to" activity depending on the selected type of link. - Click on the button **OK**. **Alternatively:** You can create link activities in the diagrams via the context menu. |image2| |image3| **Notes (restrictions in the links creation):** - The occurrence of an activity is only allowed in incompatible activity groups. .. |image0| image:: ../images/link_property_general.png .. |image1| image:: ../images/link_property_menu.png .. |image2| image:: ../images/link_property_create_1.png .. |image3| image:: ../images/link_property_create_2.png