Variance analysis ================= .. index:: Variance analysis Variance analysis view shows you the difference between the current project plan and one of the baselines according to the following criteria: |image0| - Time - Effort - Cost **Application of variance analysis:** - Visualisation of the difference between target and actual. - Detailed analysis of all parameter deviations. **You can use the variance analysis to do the following:** - Edit activities and subprojects from the actual plan. - Change the timescale. **Context menu in the Variance analysis view** |image2| - **Select baseline** – select a project state saved previously as a baseline for comparison. - **Show progress line over start date** – visualize the schedule deviations between a project state and selected baseline related to start dates. - **Show progress line over finish date** – visualize the schedule deviations between a project state and selected baseline related to finish dates. - **Show only difference** – show only activities/projects, where there is the time shift between target and actual. .. |image0| image:: ../images/control_gantt_analysis_menu_0.png .. |image2| image:: ../images/control_gantt_analysis_diagram.png