Machinery usage =============== .. index:: Machinery use You can structure Machinery usage by clicking the menu item **Start > Outline > Structure** using the following criteria: - Machine -> Project - Project -> Machine |image0| |image1| **Applications for the Machinery Usage view:** - Display of the project's demand for machines in the project. - Ressource allocation from the perspective of machines. - Calculation of the usage of every single machine. - Calculation of the total efforts and total costs of every single machine. - Visualisation of the machines allocation in activities. **You can use the Machinery Usage view for the following:** - Assign selected activities to a machine. - Analyse the machine usage by means of filter settings. - Change the timescale. - Quick access to the resource pool. **Context menu in the Machinery Usage view** If you open the context menu in the **Machine row**, the following commands appear: |image2| - **Show maximum usage per unit of the time** – the maximum required number of machine resources for each of the machine groups - machine types per day, week, etc. - **Show average usage per unit of the time** – the average required number of machine resources per day, week, etc. - **Show effort per unit of the time** – planned effort in machine hours (or machine days, respectively) per day, week, etc. If you open the context menu in the **Activity row**, the following commands are available: - **Share** - the selected activity shares the machine together with other activities. - **Use exclusively** - the selected activity uses the machine exclusively. .. |image0| image:: ../images/control_skill_structure.png .. |image1| image:: ../images/control_machinery.png :alt: Machinery .. |image2| image:: ../images/control_skill_menu.png :alt: