Project-specific team ===================== .. index:: Project-specific team You can structure team usage by clicking the menu item **Start > Outline > Structure** using the following criteria: - Team -> Project - Project -> Team |image0| |image1| Application of the Project-specific team usage view: - Display of the project's demand for resources in the form of teams for a project. - Resource allocation from the perspective of teams. - Project-specific calculation of the usage for every single team. - Project-specific calculation of the total efforts and total costs of every single team. - Project-specific visualisation of the teams assignation to activities for a project. **You can use the Project-specific team usage view for the following:** - Assign selected activities to a team. - Analyse the team usage for a project by means of filter settings. - Change the timescale. - Quick access to the resource pool. **Context menu in the Project-specific team usage view** |image2| - **Show maximum usage per unit of the time** – the maximum required number of personnel resources for each of the work groups / teams per day, week, etc. - **Show average usage per unit of the time** – the average required number of team resources / teams per day, week, etc. - **Show effort per unit of the time** – planned effort in employee hours (or employee days, respectively) per day, week, etc. .. |image0| image:: ../images/control_skill_structure.png .. |image1| image:: ../images/control_team_project.png :alt: Team project .. |image2| image:: ../images/control_skill_menu.png