Shift to resource pool ====================== .. index:: Shift to resource pool It may be that the resources used in a project differ from those in the resource pool file, because project resources are saved with the project. In this case, you can shift the project resources to the resource pool. |image0| In order to align the resources, do as follows: Select the menu item **Project > Project resource > to Resource pool** |image1| The dialogue **Choose between project resources and resource pool** will open if there are differences in resources. The first row shows the entries from the resource pool, the second row - from the project resources. |image2| - Take a minute to decide which of the following options you want to use for your work. - Choose the option **Use resource pool** to use the resource pool. - Choose the option **Replace project resources with resource pool (per code)** to replace the differing project resources data with those of the resource pool. - Choose the option **Manual selection of resources** to select manually for each deviating item. - Click on the button **OK**. **Note:** - In selecting resources manually, the dialogue **Manual selection of resources** opens in the next step. For each of the resource items you need to enter manually what you want to do with the differing resources. .. |image0| image:: ../images/normalize_message.png .. |image1| image:: ../images/normalize_menu.png .. |image2| image:: ../images/normalize.png