Project controlling =================== .. index:: Project controlling Project controlling consists of the following: - Entering information about the project progress - Setting of cutoff date - Analyse of ongoing and waiting activities **Enter information about the project progress** The updating of information about a selected activity can be accomplished by entering the activity's percentage of completion at regular intervals. In order to enter the completed activity's percentage, do as follows: - Mark the activity you want to enter in the diagram. - Activate the tab **General** in the window Activity properties. - Enter the percentage in the field **Completed**. - Click on the button **OK**. |image0| **Alternative 1:** You can enter the completion percentage in the context menu of the activity. **Alternative 2:** Select a task and click the menu item **Start > Schedule >...** |image1| **Alternative 3:** You can enter the completion percentage in the table of the Gantt chart in the columns Quantity, Effort and Duration below **Completed**. - click on **Gantt chart Format > Data > Columns** and selectthe required columns. - click on **Gantt chart Format > Data > Columns** and select Select the required columns. |image2| - Enter eg., how much effort has been completed. |image3| **Note:** If there is a number of activities linked as **Finish-Start**, and if the successor has more than 0% in the field **Completed**, its predecessor is set automatically to the value 100%. **Setting of cutoff date** A cutoff date is the point of time at which the percentages were entered last time. A cutoff date is determined by means of a check mark (a small triangle in the upper part of the timescale). Example: Gantt chart with determined cutoff date and percentages (black bar in activities). |image4| **Analyse of ongoing and waiting activities** You can view the project information by clicking on the blank space in the window of the main project. |image5| - **Completed** - Number of finished activities. - **Started** - Number of started activities. - **Still not started** - Number of activities that have not yet started. - **All** - Number of all activities. - **Reserve** - Difference in time between the finish date of the latest activity and the cutoff date of the project. - **Completed** - Percentage of the project's progress (is calculated only by means of the activities duration). - **Ongoing and waiting activities** - This list shows detailed information about activities that have just started or are ready to be started. The column **Difference** shows the deviation between the actual progress of activities at the moment and at the cutoff date (negative difference: delay / backlog, positive difference: gain of time). .. |image0| image:: ../images/project_managen3.png .. |image1| image:: ../images/project_managen2.png .. |image2| image:: ../images/project_managen1.png .. |image3| image:: ../images/project_managen0.png .. |image4| image:: ../images/project_managen4.png .. |image5| image:: ../images/project_managen5.png