Take over start and finish dates of a project from activities ============================================================= .. index:: Take over start and finish dates of a project from activities Rillsoft Project allows you to define the start and finish dates of a project during the setup of this project. |image0| A project's duration is usually set by default for two weeks. You may use the menu item **Project > Schedule > Take over** to recalculate project dates in relation to a start date of the first activity and the finish date of the last activity. |image1| .. |image0| image:: ../images/project_termin_1.png .. |image1| image:: ../images/project_termin_2.png