Late activities =============== .. index:: Late activities Click on **Start > Properties > Info** to display late activities. |image0| Select the tab **Late activities**. |image1| Late activities indicate that a project plan has not been updated by a completed percentage, but a deadline has been postponed. You can find the following information about late activities in the window: **Conflict** shows a difference between the timepoint of an activity, where the activity is not yet completed, and the deadline in working days. **Nr.** - activity number **Name** - activity name **Effort** - general activity effort for all assigned resources **Negative Effort** - shows the difference between an effort assigned to roles and the effort covered by employees. As an example. If a role with 24 Ph (3 AT) is first assigned to an activity and then to an employee who can fulfil this role. However, the employee has a nonworking day over the activity time and can fulfil only 16 Ph (2 AT). The negative effort is 24 - 16 = 8 Ph. **Duration** - activity duration **Start** - start of activity **Finish** - end of activity **Balance** - contains the dynamically calculated difference between the requested effort for a role and the summarized effort of the already assigned employees with the same role and qualification. This serves as support during the controlling of the required assignations of employees. A negative value, for instance, indicates that more employees with this role and qualification are required. .. |image0| image:: ../images/projectinfo.png .. |image1| image:: ../images/projectinfo_late_activities.png :alt: Late activities