Assign activities to a material in the view Material requirements ================================================================= .. index:: Assign activities to a material in the view Material requirements In order to assign activities to a material, do as follows: - Select the view **Start > Resource views > Material requirements**. - Select the menu item **Start > Edit > Filter**. The dialogue box **Filter** opens. |image0| - Remove the tick from the check box **Offer only used resources for selection** to view all materials from the resource pool in the list. - You can mark the check box **Material** and transfer all materials to the view Material requirements. **Alternatively**, you can mark only selected materials. - Click on the button **OK**. - Select the material which you want to assign activities to in the table of the view Material requirements. The tab **Activities** in the window Resource properties lists activities from the project schedule. |image1| - Mark the check boxes of the activities. - Among others, you can define the **material quantity** for an activity. - Mark the check boxes of the activities. - Click on the button **OK**. **Material properties during assignation** During assignation you can refine material properties by controlling and defining the following values for each activity: - Calculation of a material - Quantity of a material - Notes concerning a material. **Activity selection** During this assignation you can determine the activity list by activating /deactivating the following options: - **Assigned activities only** lists only assigned activities. **Activities at a specific date** You can filter activities that are due at a specific date. If you leftclick on a cell showing the result from the row Material and column Date, you will only receive the displayed activities that were defined for this particular time period. .. |image0| image:: ../images/filter_equipment.png .. |image1| image:: ../images/equipment_task.png