Define general activity properties ================================== .. index:: Define general activity properties In order to define the general properties of an activity, do as follows: - Activate the tab **General** in the window Activity properties. |image0| Field **Due date** - Choose the option **Start** if you have a fixed start date of the activity and enter **Date** and **Time**. The finish date of the activity will be calculated automatically. - Choose the option **Finish** if you have a fixed finish date of the activity and enter **Date** and **Time**. The start date of the activity will be calculated automatically. **Note:** You can move the start date and finish date of an activity much more quickly in the diagram by using the mouse to shift the activity. - Mark the check box **Fix** if the activity due dates in the optional date calculations that have been selected via the menu must not be shifted. - Mark the check box **Mark as milestone** if you want to label the activity as milestone. In this case, activity duration is set to zero. Field **Activity calendar** - Select the calendar you want to use from the drop down list **Activity calendar**. The button |image1| allows for the quick access to the actual calendar. - Mark the check box **Disregard team calendar and employee calendar** if the team calendar and employee calendar should not be regarded in new activities. - Mark the check box **Start of activity only at first shift** if the start of activity is permitted to begin only at the first shift. - Mark the check box **Merge into one line** if you want to have several activities succeeding in a row displayed hierarchically independent. - Enter the percentage of completion of an activity in the field **Completed**. - Enter extra costs that are not on display along with the resources in the field **Fixed costs**. Field **Financing** - Enter the amount of the payment period in the field **Invoice amount**. - Define a period of time in business days for the due date of the payment in the field **Term of payment**. - You can enter the date of the payment receipt in the field **Receipt of payment** only if you have declared the milestone to be 100% completed. Once you have marked the milestone as 100% completed, the payment receipt is displayed automatically along with the due date of the milestone plus the term of payment. You may also correct the date. - Select the color you want to use from the drop down list **Color** - Click on the button **OK**. .. |image0| image:: ../images/task_property_general.png .. |image1| image:: ../images/button_custom.png