Dynamic baseline

As a project is continually being developed and updated, none of the saved baseline plans, which is only a momentary recording the project status, can provide a complete overview.

Here comes a so-called dynamic baseline plan to help, which is automatically generated from all stored baselines.

Rillsoft Project goes through all the stored baselines and searches each activity for its last state before adding its completed percentage or effort. Exactly this activity´s version is taken over into a dynamic baseline.

Note: Requirements for a dynamic baseline

  1. Save baselines

  2. Maintain completed percentage or effort

Dynamic baseline